OUR PROCESS

From the initial consultation, to the creation of your budget, to the construction and completion of your project, the Hodge Design & Remodeling team will be with you every step of the way.


 
pinewood-2-low-res.jpg
 
 

1) Initial Consult

•     60-90 Minute meeting at clients home
•     Discuss scope of work
•     Examine existing site conditions
•     Take initial measurements
•     Take photographs of existing space

2) Budget

•    Provide Opinion of Probable Cost (OPC)
•    If construction budget falls within OPC range + or - 15%, proceed to Design Agreement

 
 
688.jpg
 
 

3) Design Agreement

•    Outline scope of work, design budget and details of the design retainer fee
•    Explain work that takes place in the design phase
•    Sign Design Agreement to proceed

4) Selections & Design Work

•     Meet with designer in our showroom to begin selections process
•     2-6 weeks design development (dependent on scope of project)
•     Meetings scheduled as needed to confirm design & selections
•    Site visit walk through with Trades to confirm project details

 
 
021_Hodge_Bath.JPG
 
 

5) Authorization to Proceed

•     Review:
-     Plans
-     Elevations
-     Selections
-     Schedule
-     Construction Contract
•     Authorize to proceed
•     Sign Contract

6) Pre-Construction

•     Meet your Project Manager
•     Pre-construction meeting with Hodge Design & Remodeling staff
•     Obtain permits
•     Create your Co-Construct account and log in to confirm

 
 
04_Exterior_Hodge.jpg.jpg
 
 

7) Construction

•  Place job sign, permit board and notification signs
•  Set up dust control
•  Progress reports daily in Co-Construct
•  Job site broom cleaned daily
•  Job site vacuum cleaned weekly
•  Payments follow milestones throughout the construction phase, as noted in your contract.

8) Completion

•     At substantial completion, a meeting is scheduled to discuss and address (if any) punch list items
•     Substantial completion payment due less retainer for any punch list items
•     When punch list is complete retainer is due
•     Written one-year warranty provided along with NAHB residential performance guidelines.
•     Photographs of finished project scheduled
•     Follow up calls at 6 months and 1 year to check in

 
 
 

Larry can calmly redirect a wild client idea into something that his knowledge and experience knows will actually work. He took our list of wants and transformed them into a contemporary design better than we could have ever dreamed of. Everyone who has seen it is also in awe of the light, the balance, and the creative elements. We HIGHLY recommend Hodge Design & Remodeling.
— Shannon Bayless

Download our Process Brochure
Hodge Design & Remodeling Process:

Still have questions? No problem!
Read our Remodeling Budget: What to Expect page:


 

Contact Us TODAY, to see how we can bring your vision to life: